Council is undertaking a major project in the Branyan area - widening of the existing 6 metre sealed section of Bonna Road from Isis Highway to just South of Bush Road - to an 8 metre section with some realignment of existing curves.
The upgrade will also include installation of new stormwater components throughout the length of the project.
This map shows the site of the works:
Council is utilising an open market tender to award the construction to a suitably qualified Principal Contractor.
Council will advise of the successful tenderer on award and provide contact details for onsite issues such as traffic management and staging of the works to affected residents.
Timeline is currently for construction from March to July 2024.
Update February 2024
SGQ Pty Ltd have been awarded the Bonna Road Widening Contract.
Construction is due to begin early March 2024
Currently the project is estimated to take approximately 5 months, weather permitting.
Construction activities are expected to be carried out between the following hours:
6:30 am and 6:00 pm, Monday to Friday
7:00 am and 2:30 pm Saturday, as required.
Works will be undertaken using traffic control and some lane closures.
Access to private properties adjoining the work areas will be maintained during the construction period.
Residents can expect changes to traffic conditions during this time and delays may be experienced.
Find out more details in the latest newsletter here.
Council is undertaking a major project in the Branyan area - widening of the existing 6 metre sealed section of Bonna Road from Isis Highway to just South of Bush Road - to an 8 metre section with some realignment of existing curves.
The upgrade will also include installation of new stormwater components throughout the length of the project.
This map shows the site of the works:
Council is utilising an open market tender to award the construction to a suitably qualified Principal Contractor.
Council will advise of the successful tenderer on award and provide contact details for onsite issues such as traffic management and staging of the works to affected residents.
Timeline is currently for construction from March to July 2024.
Update February 2024
SGQ Pty Ltd have been awarded the Bonna Road Widening Contract.
Construction is due to begin early March 2024
Currently the project is estimated to take approximately 5 months, weather permitting.
Construction activities are expected to be carried out between the following hours:
6:30 am and 6:00 pm, Monday to Friday
7:00 am and 2:30 pm Saturday, as required.
Works will be undertaken using traffic control and some lane closures.
Access to private properties adjoining the work areas will be maintained during the construction period.
Residents can expect changes to traffic conditions during this time and delays may be experienced.
Find out more details in the latest newsletter here.
Page last updated: 08 Apr 2024, 03:18 PM
Follow Project
Stay informed
Subscribe for project updates
Timeline
Open market tender to award the construction to a suitably qualified Principal Contractor
Bonna Road Widening has finished this stage
Awarding of Contract
Bonna Road Widening has finished this stage
SGQ Pty Ltd have been awarded the Bonna Road Widening Contract.
Traffic management update to be provided prior to works commencing onsite.
Bonna Road Widening has finished this stage
Construction to begin
Bonna Road Widening is currently at this stage
March, 2024: SGQ will commence works onsite.
Currently the project is estimated to take approximately 5 months, weather permitting. Construction activities are expected to be carried out between 6:30 am and 6:00 pm, Monday to Friday and 7:00 am and 2:30 pm Saturday, as required. Works will be undertaken using traffic control and some lane closures.
Access to private properties adjoining the work areas will be maintained during the construction period.
Residents can expect changes to traffic conditions during this time and delays may be experienced.