Hughes Road / Blain Street Roundabout

Share Hughes Road / Blain Street Roundabout on Facebook Share Hughes Road / Blain Street Roundabout on Twitter Share Hughes Road / Blain Street Roundabout on Linkedin Email Hughes Road / Blain Street Roundabout link

April 2025 Project Update

Works are continuing on the Hughes Road / Blain Street Roundabout,

• The wet weather experienced early April resulted in some minor delays.
• Civil contractor has installed all the underground sub-soil drainage to capture any water infiltration that enters the site now and in the future.
• Grader commenced work just prior to Easter to allow for the importing of gravel to build the roadway.
• Ergon have been on site to install the new underground cabling in the conduits provided by electrical contractors.
• Ergon have connected the new power source and removed any unwanted power poles and works are now complete.

All businesses and the Childcare Centre on Hughes Road remain open and accessible from the southern end of Hughes Road from the Wessells Road, Causeway Drive and Hughes Road intersection.

All works are subject to weather conditions.

March 2025 Project Update

Work for the construction of the Hughes Road / Blain Street roundabout is progressing well. Detours and signage remain in place to inform and direct road users to alternate routes. The businesses on Hughes Road remain open and can be accessed by turning on to Seaview Road from Bargara Road then from the southern end of Hughes Road at the Wessels / Watsons Road intersection.

Works to date have included:

  • Installation works for the new conduits to accommodate Ergon infrastructure was completed by 14 March, with the trench backfilled and ready for Ergon to commence their work.
  • Ergon have attended the site and installed two (2) new power poles as well as the new high voltage cabling required underground.
  • A substantial amount of work has been undertaken by the Civil Contractor with the roadway now taking shape. Base material has been put in place and compacted to industry standards.
  • The current wet weather we are experiencing has resulted in small delays.

All works are subject to weather conditions.

February 2025 Project Update

The full road closure of a section of Hughes Road is currently in place and construction of the roundabout at the intersection of Hughes Road / Blain Street has now commenced.

Works to date have included:

  • Electrical contractors have commenced installing new conduits to accommodate Ergon infrastructure. These installation works are scheduled to be completed by 14 March.
  • Council's internal Water Services crew have relocated the existing water main to avoid any conflicts during the construction works.
  • The civil works contractor has commenced importing additional material to build the roadway up to match the adjoining new development works and will continue the demolition works of the existing infrastructure.
  • Ergon are scheduled to commence relocation works from the 14 March with an estimated completion date of 31 March.
  • Council's internal Water Services crew are constructing new sewer access chambers and a new sewer main across Hughes Road to service the new sewage infrastructure network being installed at the new development at 76 Hughes Road. While these works do not form part on the intersection upgrade, they are being carried out while the road closure is in place to avoid any further delays.

All works are subject to weather conditions.

January 2025 Project Update

A full road closure on a section of Hughes Road is scheduled from 10 February 2025 to allow works for the construction of the Hughes Road / Blain Street roundabout to commence. Detours will be in place to inform and direct road users to alternate routes. Please refer to the below sketch for closure and detour information. The businesses on Hughes Road will remain open while the road closure is in place with access from the southern end of Hughes Road at the Wessels / Watsons Road intersection.

Works currently scheduled:

  • Relocation of water main will commence on 22 January with no effect to traffic flows.
  • Relocation of Ergon infrastructure scheduled to commence on 10 February.
  • Ergon on-site to install new cabling, remove nominated power poles and overhead power lines.
  • Telstra relocations will commence following completion of water main and Ergon infrastructure relocations.
  • Civil works tender for construction closed on 21 January. Contractor and construction commencement dates TBA.

All works are subject to weather conditions.

November 2024 Project Update

Council has awarded an electrical contractor for the installation of the Ergon conduits with an expectation to commence works by late January / early February 2025.

The relocation of services is to be carried out from end of January to end of February and this will include, installation of Ergon conduits, cabling and removal of power poles, Telstra relocations and the realignment and relocation of water main. Road closures will be in place for a period of 2 weeks (dates to be confirmed) while these works are being carried out.

The Civil works component is intended to commence beginning of March, this will include an extended period of time that there will be a road closure in place while works are being carried out. The expected completion date is mid-June 2025.

Council encourages all road users to seek alternate route and apologises for any inconvenience that these road closures may cause.

Project Background

The Hughes Road/Blain Street intersection upgrade project will be delivered as part of the Bundaberg Regional Council 2024/2025 budget.

The project was identified as part of the Bargara Emerging Communities Infrastructure Planning (ECIP) project which won an Institute of Public Works Australasia (QNT) Innovation and Sustainability in Water award and a Stormwater Queensland Excellence in Strategic or Master Planning award in 2023.

The intersection will be upgraded to a roundabout in response to the ongoing development along Hughes Road and, in particular, the planned extension of Blain Street further west.

A roundabout in this location ensures a safe intersection for all road users and will specifically feature safe crossings for pedestrians and cyclists to ensure connectivity for active modes of transport between new development and the township of Bargara.

Business Access

Council is committed to working with businesses along Hughes Road to minimise disruption and give safe access to staff, suppliers and customers.


Stay informed

Council can keep you informed during all phases of construction. Register on the Stay Informed section at the top right hand side of this page to get the latest information.

April 2025 Project Update

Works are continuing on the Hughes Road / Blain Street Roundabout,

• The wet weather experienced early April resulted in some minor delays.
• Civil contractor has installed all the underground sub-soil drainage to capture any water infiltration that enters the site now and in the future.
• Grader commenced work just prior to Easter to allow for the importing of gravel to build the roadway.
• Ergon have been on site to install the new underground cabling in the conduits provided by electrical contractors.
• Ergon have connected the new power source and removed any unwanted power poles and works are now complete.

All businesses and the Childcare Centre on Hughes Road remain open and accessible from the southern end of Hughes Road from the Wessells Road, Causeway Drive and Hughes Road intersection.

All works are subject to weather conditions.

March 2025 Project Update

Work for the construction of the Hughes Road / Blain Street roundabout is progressing well. Detours and signage remain in place to inform and direct road users to alternate routes. The businesses on Hughes Road remain open and can be accessed by turning on to Seaview Road from Bargara Road then from the southern end of Hughes Road at the Wessels / Watsons Road intersection.

Works to date have included:

  • Installation works for the new conduits to accommodate Ergon infrastructure was completed by 14 March, with the trench backfilled and ready for Ergon to commence their work.
  • Ergon have attended the site and installed two (2) new power poles as well as the new high voltage cabling required underground.
  • A substantial amount of work has been undertaken by the Civil Contractor with the roadway now taking shape. Base material has been put in place and compacted to industry standards.
  • The current wet weather we are experiencing has resulted in small delays.

All works are subject to weather conditions.

February 2025 Project Update

The full road closure of a section of Hughes Road is currently in place and construction of the roundabout at the intersection of Hughes Road / Blain Street has now commenced.

Works to date have included:

  • Electrical contractors have commenced installing new conduits to accommodate Ergon infrastructure. These installation works are scheduled to be completed by 14 March.
  • Council's internal Water Services crew have relocated the existing water main to avoid any conflicts during the construction works.
  • The civil works contractor has commenced importing additional material to build the roadway up to match the adjoining new development works and will continue the demolition works of the existing infrastructure.
  • Ergon are scheduled to commence relocation works from the 14 March with an estimated completion date of 31 March.
  • Council's internal Water Services crew are constructing new sewer access chambers and a new sewer main across Hughes Road to service the new sewage infrastructure network being installed at the new development at 76 Hughes Road. While these works do not form part on the intersection upgrade, they are being carried out while the road closure is in place to avoid any further delays.

All works are subject to weather conditions.

January 2025 Project Update

A full road closure on a section of Hughes Road is scheduled from 10 February 2025 to allow works for the construction of the Hughes Road / Blain Street roundabout to commence. Detours will be in place to inform and direct road users to alternate routes. Please refer to the below sketch for closure and detour information. The businesses on Hughes Road will remain open while the road closure is in place with access from the southern end of Hughes Road at the Wessels / Watsons Road intersection.

Works currently scheduled:

  • Relocation of water main will commence on 22 January with no effect to traffic flows.
  • Relocation of Ergon infrastructure scheduled to commence on 10 February.
  • Ergon on-site to install new cabling, remove nominated power poles and overhead power lines.
  • Telstra relocations will commence following completion of water main and Ergon infrastructure relocations.
  • Civil works tender for construction closed on 21 January. Contractor and construction commencement dates TBA.

All works are subject to weather conditions.

November 2024 Project Update

Council has awarded an electrical contractor for the installation of the Ergon conduits with an expectation to commence works by late January / early February 2025.

The relocation of services is to be carried out from end of January to end of February and this will include, installation of Ergon conduits, cabling and removal of power poles, Telstra relocations and the realignment and relocation of water main. Road closures will be in place for a period of 2 weeks (dates to be confirmed) while these works are being carried out.

The Civil works component is intended to commence beginning of March, this will include an extended period of time that there will be a road closure in place while works are being carried out. The expected completion date is mid-June 2025.

Council encourages all road users to seek alternate route and apologises for any inconvenience that these road closures may cause.

Project Background

The Hughes Road/Blain Street intersection upgrade project will be delivered as part of the Bundaberg Regional Council 2024/2025 budget.

The project was identified as part of the Bargara Emerging Communities Infrastructure Planning (ECIP) project which won an Institute of Public Works Australasia (QNT) Innovation and Sustainability in Water award and a Stormwater Queensland Excellence in Strategic or Master Planning award in 2023.

The intersection will be upgraded to a roundabout in response to the ongoing development along Hughes Road and, in particular, the planned extension of Blain Street further west.

A roundabout in this location ensures a safe intersection for all road users and will specifically feature safe crossings for pedestrians and cyclists to ensure connectivity for active modes of transport between new development and the township of Bargara.

Business Access

Council is committed to working with businesses along Hughes Road to minimise disruption and give safe access to staff, suppliers and customers.


Stay informed

Council can keep you informed during all phases of construction. Register on the Stay Informed section at the top right hand side of this page to get the latest information.